Leverone Field House

About the project

The Leverone Field House is currently undergoing a replacement of the building's roof and a renewal of its mechanical, electrical, and fire protection systems. Originally built in 1965 by Italian architect Pier Luigi Nervian–an early adopter of reinforced concrete construction in public spaces–the building was previously renovated in 2000. For more insight into the project, take a look at the Interactive 3D map of Leverone Field House. 

Project Goals

  • Replace and insulate the existing roofing.  

  • Replace the lighting and fire alarm systems. 

  • Convert the heating system from steam to hot water. 

  • Install an air conditioning system. 

Project Timing

  • The south-facing portion of the roof has an anticipated completion date of fall 2024. 

  • The north-facing portion of the roof and new HVAC system has an anticipated completion date of winter 2025. 

What's currently happening

  • Completed Phase 1 of the south-facing portion of Leverone's roof replacement in fall 2024.
  • Closure of Leverone begins March 17 to Dartmouth students and faculty. Only construction personnel will be allowed in Leverone moving forward until October 2025
  • The construction team is mobilizing for Phase 2 of the north-facing roof replacement and the steam to hot water upgrades, beginning in mid-March to October 2025.
  • Installation of plywood to cover all existing Leverone flooring to provide surface protection from roof replacement construction work
    • Installation of temporary fencing near Memorial Football Field to prepare for the arrival and placement of ground storage boxes
    • Continuing the relocation of all sports equipment from Leverone into ground storage boxes and designated storage areas, with a final moving date of March 31.
    •  Arrival of boom lift onto Leverone site.
    • Erection of temporary tent at the Friends of Football Lot to serve as track and field's temporary weightlifting area throughout duration of construction