As part of President Sian Leah Beilock's commitment to add 1,000 beds for faculty, staff, and students in the next 10 years, Dartmouth is financing a $15.2 million housing development south of campus in West Lebanon, N.H., for Dartmouth employees. The 21-unit development will feature 14 two-story, three-bedroom homes; three duplexes with a total of five three-bedroom units and one two-bedroom unit; and one single-story, three-bedroom home designed for accessibility. The project is located off Route 10 on five acres off of Oak Ridge Road, and all units will include a single-car garage.  

Project Goals

  • Help meet pressing housing needs in the Upper Valley. 

  • Improve Dartmouth's ability to attract and retain the best faculty and staff by creating high-quality housing for employees close to campus. 

  • Control costs, ensure energy efficiency, and accelerate the building process by utilizing a modular construction model. 

Project Timing

  • The City of Lebanon has approved the next two foundations, and concrete work is re-commencing.
  • The first home will be delivered in four sections.
  • The crane crew will complete the setting of the four sections onto the foundation in late May.
  • The second home will be delivered and placed onto the foundation in early June.

What's Currently Happening

  • Seven Foundations are poured and ready to receive a new home. 
  • The first home will be delivered in four sections next week and placed on its foundation the week of May 12th.
  • The developer received Lebanon Planning Board permission to install all 18 foundations immediately to enable them to complete most soil work this spring.  
  • The current schedule has all structures on the site by April 2026.

Project Team

  • Project Developer: Occom Path, Inc. 

  • Builder: Huntington Homes and Estes and Gallup 

  • Contact: Dan Justynski, Dartmouth Real Estate Office, 603-646-2654