DOC House Class of '69 Renovation

Update for the two weeks beginning Mar. 1 and 8, 2021

About the Project

The DOC House is currently closed for renovations to make capital renewal improvements and preserve the building's early 1920's character. This historical building is scheduled to reopen in June, 2021 to host special events. In the winter, the DOC House will continue to serve as home to the Dartmouth Ski and Skate Center. 

Renovations are being funded by Dartmouth's Class of '69 in honor of their 50th College reunion.

What's Happening

  • The interior rough-in for MEP is 95% complete.
  • Exterior roof trim has started.
  • New window installations are underway.
  • Installation of new sheetrock begins.
  • Roof installation is ongoing.

What to Expect

  • Regular work hours will be Monday – Friday, between 8 a.m. – 6 p.m., in accordance with town regulations.
  • Construction signage and fencing will be in place throughout the project.
  • The DOC House will be closed during renovations.